Being modernized Mutnovsky geothermal power plants
date: 2014-09-02 14:55:59

According to the JSC "Geoterm" on Mutnovsky Geothermal Power Geothermal Power Plant started the planned modernization in preparation for the cold period of 2014-2015,. Modernization process is performed preventive maintenance (CPD) of the production program and PPR schedule.

Who works on major repair of the turbine rotor with the extraction installation, repair work on the foundation supports UWC (air-capacitor installation) and replacement of fire tanks on the Upper Mutnovskaya Geothermal Power Plant. AT UWC will also be replaced cooling panels on corrosion-resistant.

Next, plan to upgrade Stanzione automated process control system (PCS) with a planned replacement microprocessor APCS 1 unit that will ensure high automation according to international standards. Geothermal field reconstructed production well A-3, and repaired the foundations of pipelines with complete replacement of the insulating equipment.

Repair work will be completed August 30, 2014 In the outage load geothermal power plant will take the Kamchatka CHP. Repair program for Mutnovskaya GeoPP Geoterm estimated 38.5 million rubles.

To list



Share:
Our socials: